County gets update on fall construction
Commissioners also discuss renewing contract with CEDA for next year
The replacement of a bridge on County State Aid Highway 8 with a box culvert has been progressing now that the weather has been cooperating. The road should reopen soon.
The Faribault County Board of Commissioners received some good news at their meeting on Oct. 20 when Public Works director/county engineer April Wellman updated the board on the bridge work on County State Aid Highway (CSAH) 8.
“The box culvert is set, the water is flowing and it is being backfilled,” Wellman reported. “It is tentatively scheduled to be paved after the bridge in Kiester Township is paved.”
Wet weather had caused delays in installing the box culvert and completing the bridge work on the CSAH 8 project.
“I am hoping the road will be open by the end of this week. But I make no guarantees on that,” Wellman emphasized.
Wellman said work on another bridge project, located in Pilot Grove Township, had started on Oct. 12.
“After that, the bridge in Delavan Township will be next,” Wellman commented. “Following that, the bridge replacement in Lura Township will be the last one for the year.”
Wellman’s update on the 2027 construction plans included news that CSAH 7 was being milled as of Oct. 20 and CSAH 20 milling is scheduled to start next week.
“They will sit over the winter,” she said. “We will use dust control on the roads as needed.”
Wellman shared there are three county bridges scheduled for replacement next year.
“One is west of Kiester on CSAH 2,” she stated. “The other two are in Clark and Pilot Grove townships.”
Next, the board spent quite a bit of time discussing the contract the county has with CEDA (Community and Economic Development Associates).
“Our contract with the county is a one-year contract,” CEDA regional manager Dave Schmidt reminded the board. “The contract runs from Jan. 1 through Dec. 31.”
Currently, Faribault County has a four-day-per-week/32 hours per week contract with CEDA which is staffed two days by EDA (Economic Development Authority) specialist Jim Langborg and two days by EDA specialist Danielle Hayter-Johnson.
“The proposed contract for 2027 is $96,121, which is a four percent increase over the current year’s contract of $92,423,” Schmidt explained. “We were originally looking at a five and a half percent increase but have decreased that to four percent.”
The question was raised on what the cost would be for a three-day-per-week contract.
“A three-day contract would be over $80,000,” Schmidt stated. “There is a cost break that comes with contracting more days per week. For instance, a contract for one day per week is around $34,000. When contracting with CEDA, you not only get the days per week you pay for, you also get access to the 50-plus employees in CEDA who have expertise in a wide variety of areas.”
The amount of the total proposed budget for the Faribault County EDA for 2027 is $129,842 with the bulk of the expense attributed to labor.
Board members decided to wait to take any action on the proposed contract until they are able to consider the complete county budget for 2027.
Shawn Bococcini of Project Blue Financial, who had spoken to the board at a previous meeting, returned via Zoom to talk about his company’s Preventative Health Initiative (PHI), which is a program designed to reduce employer FICA costs while providing employee benefits like telehealth, wellness coaching and family support.
“The program is structured to be net-cost-neutral for businesses, often yielding an average FICA tax reduction of about $500 per employee annually,” Bococcini said. “It is funded through strategic payroll and tax credit structuring rather than direct out-of-pocket overhead, thus making it zero net cost. It is not a mandatory program, employees can opt in if they want.”
The board voted to offer the program to county employees.
The board also approved a motion maintaining the employee portion of health insurance premium costs to the same levels in place from 2025 to 2026.
In other business, the board:
• Recognized Lincoln Reynolds for one year of service in the Sheriff’s Department, Dayton Enger for one year of service in the Buildings and Grounds Department, Jennifer Howard for one year of service as the Faribault County Veteran Services Officer and Mark Wallin for 15 years of service in the Public Works Department.
• Approved the purchases of new panic button system equipment at at cost of $5,188.
• Voted to approve the purchase of a custom-cut stone block from Vetter Stone at a cost of $1,000. The block will be placed at the northwest corner of the original courthouse building to help prevent erosion on some severely sloped soil.
• Approved the training request of Michael Sharp of the Sheriff’s Department to attend Crisis Intervention Training.
• Approved the request Bryan Schaper of the Public Works Department to take Introduction to Surveying Training.